Assigning Changes to a Release

  

DEVELOPER

You must assign the changes using Release Management Console or Change Management Console.

If you want to reassign a change to a different release, view the changes on the release, select the required change and click Amend Change to open the Maintain Change Number window. Select the required release and click OK.

To assign changes to a release:

  1. Locate and select the release on the Release Management Console.

  2. Click Assign to open the Assign Changes to a Release window.
    All pending changes are displayed.

  3. Select the object(s) to assign to the release and click Assign. Use Ctrl+click and Shift+click to select multiple objects.

  4. To assign all objects on the list, click Assign All.

  5. Click Exit.

The following table explains the fields:

Item

Description

Release

The name of the release.

Change

The name of the change.

Description

The description of the change.

Current Region

The current region.

Status

The status of the change: pending approval or approved.

Approved

The date the change was approved. Note that if the change has been unapproved the date the change was initially approved appears even if the status in region is pending approval.

Approved By

The ID and name of the user that approved the change.

Added

The date the change number was created.

Added By

The ID and name of the user that created the change.

Assign

Assigns the selected changes to the release.

Assign All

Assigns all changes to the release.

Exit

Closes the Assign Changes to a Release window.


 